Apache Data Center

  • Owner: Apache Corporation
  • Contractor: SpawMaxwell Company
  • Date Completed: 01/07
  • Contract: $3,100,000

The project included the installation of a new 1500 KW generator, 2- 500 kVA UPS’s, and all associated transfer switches, switchgear, PDU’s, & static transfer switches  to the existing 24 story building. The UPS room was located in the parking garage adjacent to the building and the data center was located on the 9th floor.  The project was on a fast track schedule and required extensive coordination with the design team in a design assist role. Our assistance was used to facilitate the primary location of the new 2500 amp buss through the existing garage, basement and up to the 9th floor with 67 elevation changes in the distribution buss duct and feeders.